Abstract
Many construction projects are delayed due to a range of factors, including the unique spatial and environmental context of every construction site, the challenges of maintaining quality, and the timing of decision making around design. In consequence, construction contracts include mechanisms to accommodate delay while maintaining enforceability. Different standard forms of contract (SFC) adopt different approaches to managing delay and lack consistency in accommodating delays of the same nature. This study selects two SFCs commonly used in UK construction projects, new engineering contract (NEC) and joint contracts tribunal (JCT) suites, and proposes a common approach to managing delays, focusing particularly on the handling of the compensation event (CE) and relevant event (RE) mechanisms in those respective contracts. Using a qualitative methodology, a multi-case study analysis was conducted comprising four general contractors utilizing JCT and NEC SFCs. The case studies enabled the analytic comparison of delay-caused challenges as between different projects delivered using different SFCs. The findings reveal that while on JCT-based projects general contractors have typically suffered cash flow and programming issues caused by employer failures to adhere to contractual time scales for assessing requests for extensions of time, on NEC-based projects general contractors have suffered CE-related issues associated with programming and administration. Further findings were that the common challenges of both CE and RE management processes were high volume, assessment and time scales of claims, as well as timing and collaboration. Developing from these findings, recommendations are made for additional clauses to be added to SFCs to achieve a consistent approach toward construction delays.
Original language | English |
---|---|
Article number | 04524030 |
Pages (from-to) | 1-11 |
Number of pages | 11 |
Journal | Journal of Legal Affairs and Dispute Resolution in Engineering and Construction |
Volume | 17 |
Issue number | 1 |
Early online date | 7 Oct 2024 |
DOIs | |
Publication status | E-pub ahead of print - 7 Oct 2024 |
Keywords
- Compensation Events (CE)
- Contractors
- construction industry
- Extension of time (EoT)
- Healthcare projects
- Standard forms of Contract (SFC)
- Standard forms of contract (SFC)
- Compensation events (CE)
- Construction industry