Skip to main navigation Skip to search Skip to main content

Contractors' Perspectives on Delays in Healthcare Projects: A Tale of Two Contrasting Provisions

Niraj Thurairajah, Akila Rathnasinghe*, Charlie Roberts, Brodie McAdam, Allan Abwunza

*Corresponding author for this work

Research output: Contribution to journalArticlepeer-review

123 Downloads (Pure)

Abstract

Many construction projects are delayed due to a range of factors, including the unique spatial and environmental context of every construction site, the challenges of maintaining quality, and the timing of decision making around design. In consequence, construction contracts include mechanisms to accommodate delay while maintaining enforceability. Different standard forms of contract (SFC) adopt different approaches to managing delay and lack consistency in accommodating delays of the same nature. This study selects two SFCs commonly used in UK construction projects, new engineering contract (NEC) and joint contracts tribunal (JCT) suites, and proposes a common approach to managing delays, focusing particularly on the handling of the compensation event (CE) and relevant event (RE) mechanisms in those respective contracts. Using a qualitative methodology, a multi-case study analysis was conducted comprising four general contractors utilizing JCT and NEC SFCs. The case studies enabled the analytic comparison of delay-caused challenges as between different projects delivered using different SFCs. The findings reveal that while on JCT-based projects general contractors have typically suffered cash flow and programming issues caused by employer failures to adhere to contractual time scales for assessing requests for extensions of time, on NEC-based projects general contractors have suffered CE-related issues associated with programming and administration. Further findings were that the common challenges of both CE and RE management processes were high volume, assessment and time scales of claims, as well as timing and collaboration. Developing from these findings, recommendations are made for additional clauses to be added to SFCs to achieve a consistent approach toward construction delays.
Original languageEnglish
Article number04524030
Pages (from-to)1-11
Number of pages11
JournalJournal of Legal Affairs and Dispute Resolution in Engineering and Construction
Volume17
Issue number1
Early online date7 Oct 2024
DOIs
Publication statusPublished - 1 Feb 2025

UN SDGs

This output contributes to the following UN Sustainable Development Goals (SDGs)

  1. SDG 9 - Industry, Innovation, and Infrastructure
    SDG 9 Industry, Innovation, and Infrastructure
  2. SDG 12 - Responsible Consumption and Production
    SDG 12 Responsible Consumption and Production

Keywords

  • Compensation Events (CE)
  • Contractors
  • construction industry
  • Extension of time (EoT)
  • Healthcare projects
  • Standard forms of Contract (SFC)
  • Standard forms of contract (SFC)
  • Compensation events (CE)
  • Construction industry

Fingerprint

Dive into the research topics of 'Contractors' Perspectives on Delays in Healthcare Projects: A Tale of Two Contrasting Provisions'. Together they form a unique fingerprint.

Cite this